Barn Renovations Week 1

Post Construction is ready to go!  Alex, the site supervisor, and Herman Post discussing plans as the skid steer arrives on site.  Getting ready to sandblast existing stalls, grills, and hay feeders replacing any bad boards.  Old electrical and plumbing is out, will all be replaced and a new ceiling is coming (spray insulation thankfully pre-existing).  Stall floors to be re-levelled and matted.  New bigger windows coming to all the stalls too!  Six run-ins to be completely redone in the next couple of weeks, all fencing to be replaced soon as well.  Here also are the engineered drawings of the extensive addition planned by Post Construction.  The old tack room is being gutted and this area will become part of the new structure with a new main entrance, new stalls, wash racks, feed room, tack room, office and two level viewing of new 200' X 84' arena.  Also note new covered storage for manure and bedding.  We are all so excited!  New pictures coming soon…..